Milling along Bowness Road N.W. is complete, and crews will start paving Monday, September 13, 2021. While crews are paving Bowness Road we will need to close the road to traffic, and detour eastbound and westbound traffic around the work area. There will be flaggers on site to direct traffic while this work is happening, and sidewalks will be open. Access to residential and business driveways will be restricted while crews are milling and paving each section along Bowness Road.
We will be paving Bowness Road in sections to minimize the impact to residents, businesses, and commuters in the area as much as possible.
Home Road to 43 Street N.W.
September 13-14, 5 a.m. to 10 p.m. daily
- Crews will do the first layer of paving in this section of Bowness Road between September 13 and 14.
- Flaggers will be on site while crews are working to direct traffic to detour routes.
43 Street to Mackay Road N.W.
September 15 – 16, 5 a.m. to 10 p.m. daily
- Crews will pave this section of Bowness road September 15 and 16.
- Flaggers will be on site while crews are working to direct traffic to detour routes.
Home Road to 43 Street N.W.
September 17 and September 20, 5 a.m. to 10 p.m. daily
- Crews will do the final layer of paving along this section of Bowness Road September 17 and 20.
- Flaggers will be on site while crews are working to direct traffic to detour routes.
Home Road to 49 Street N.W.
September 21, 5 a.m. to 10 p.m.
- Crews will pave this section of Bowness Road September 21, 2021.
- Flaggers will be on site while crews are working to direct traffic to detour routes.
49 Street to 52 Street N.W.
September 22, 5 a.m. to 10 p.m.
- Crews will pave this section of Bowness Road September 22, 2021.
- Flaggers will be on site while crews are working to direct traffic to detour routes.
52 Street N.W intersection to the bridge
September 23, 5 a.m. to 10 pm.
- Crews will pave this section of Bowness Road September 23, 2021.
- Flaggers will be on site while crews are working to direct traffic to detour routes.
This work is weather dependent, and dates may change as crews move from section to section. We encourage you to visit calgary.ca/montgomerymainstreet for up to date information on when, and where crews are working.
The new Montgomery Main Street includes:
- A family-friendly, safe street that focuses on the needs of the community.
- Providing a balance of transportation options, including pedestrian and cyclist improvements
- A reconstructed roadway, sidewalks, and new pathways.
- Better access to public transit, local parks, and the river pathway.